Semi-Gantry Cranes & Overhead Cranes Installed at a Steel Processing Plant

In a recent project, our company provided a range of crane equipment for a steel processing plant in Russia. This installation included both 10 ton overhead cranes and 10 ton & 16 ton semi-gantry cranes designed to meet the plant’s operational needs and enhance its productivity. The equipment was selected to cater to different aspects of the plant’s operations, ensuring efficient handling of steel materials both inside and outside the workshop.

10 Ton Semi Gantry Crane in Russia

Crane Equipment Details

10 Ton Single Girder Overhead Cranes

Overhead Cranes:

  • Model: European Standard 10-ton Single Girder Bridge Crane
  • Quantity: 6 units
  • Span: 16.5 meters
  • Lifting Height: 8 meters
  • Work Duty: A5
  • Installation Location: Inside the workshop
Semi Gantry Crane in Russia

Semi-Gantry Cranes:

  • Model: European Standard 10-ton & 16-ton Semi-Gantry Crane
  • Span: 17.5 meters
  • Lifting Height: 7.6 meters for 10 ton crane, 7.4 meters for 16 ton crane
  • Work Duty: A5
  • Installation Location: Outside the workshop for handling outdoors

Production and Delivery of Overhead And Gantry Cranes to Russia

Manufacturing Quality: To ensure that the gantry and overhead cranes met high standards of quality and performance, rigorous quality control measures were implemented throughout the manufacturing process. The cranes were built to European standards, guaranteeing reliability and durability in the demanding environment of a steel processing plant.

Overhead Gantry Crane Manufacturing

Delivery: We reinforced the packaging of these overhead and gantry cranes to prevent any damage during transportation, which was crucial in ensuring that the equipment arrived at the site in optimal condition. Additionally, we adhered to a strict timeline to ensure timely delivery, minimizing any potential delays in the project schedule.

Overhead Gantry Crane Delivery

Installation and Operation of Overhead Gantry Cranes in Russia

Installation Guidance: We provided timely and detailed installation guidance to the client’s installation team. This support included step-by-step instructions and troubleshooting assistance to ensure that the cranes were installed correctly and functioned as intended.

Operational Status: Following installation, all overhead gantry cranes were put into operation smoothly. The comprehensive guidance we provided ensured that the cranes were integrated into the plant’s operations without any issues, facilitating work efficiency and safety.

Conclusion

This project shows our commitment to delivering high-quality crane equipment and reliable service to our clients worldwide. By ensuring that each aspect of the project – from manufacturing and delivery to installation and operation – met our stringent standards, we were able to significantly improve the efficiency, safety, and reliability of the lifting operations at the steel processing plant in Russia. We continue to focus on delivering tailored lifting solutions to meet our clients’ needs. Contact us to see how we can support your heavy lifting requirements.

    Customize Your Lifting Solutions

    Contact us now via email: inquiry15@aicranes.com, or fill in the form below.

    FEW TIPS:

    1.Load capacity: ton?

    2.Span of the crane: m?

    3.Max. lifting height of the crane: m?

    4.What materials will be handled: ?

    5.How many hours will the crane work per day?

    6.Project introduction: project working site, project budget, etc.